NetworkRail have been preparing to relay the down line in Highertown Tunnel preparation work started on Saturday 9th & Sunday 10th of May, long welded rail was delivered on Thursday 13th of May, the track is due to be relayed over this weekend 16th & 17th of May, Tamping is planned for Friday 29th & Saturday 30th of May, Sunday the 31st of May follow up work will be done and finally on Friday 10th & Saturday 11th of July follow up Tamping will take place. By Mick House
Plant In Truro yard By Mick House
For more photos go to the Engineering Plant Diary section.
Whats New at Newcourt David Tozer Reports
- 12/05/2015
Keith, Newcourt is now nearing completion. I have read on one website it could possibly open on 19th May 2015. We shall see. Dave Many thanks for your report David